An SBEM calculation is the output; an SBEM assessment is how you get there – the review of your drawings, the data collection, and the modelling that turns a set of architectural plans into a Building Control submission. Knowing what that process actually involves, and who’s qualified to run it, matters most when you’re gathering information for the first time or trying to work out why a submission has stalled.

An SBEM assessment has to be carried out by an accredited Level 4 or Level 5 Energy Assessor, depending on the building’s complexity – Level 4 covers simpler, single-system buildings, while Level 5 is required for larger or more complex ones with multiple HVAC systems or zones. For what SBEM actually measures and which buildings need one, see our SBEM Calculations guide.

  1. Initial review. The assessor works through your architectural plans, sections and M&E specifications to understand the building’s layout and systems before any modelling starts.
  2. Data collection. The building’s geometry (size and shape) and construction materials go into the software – U-values for walls, floors, roof and glazing, plus any renewable technologies like solar PV or heat pumps.
  3. Systems analysis. Heating, cooling, ventilation and lighting details are added, since these drive a significant share of the building’s calculated energy use.
  4. Simulation. The assessor runs the model and compares your “Actual Building” against the theoretical “Notional Building” the regulations require it to beat. If it doesn’t pass, this is the stage where cost-effective fixes – better lighting controls, improved insulation, adjusted glazing – get identified and tested before resubmission.
  5. Certification. Once compliant, the assessor issues the BRUKL Report for Building Control, and – at As-Built stage – the Commercial EPC.
DesignBuilder 3D model of a commercial building with a solar path diagram overlaid, showing sun position by month and time of day used in SBEM energy modelling.
DesignBuilder energy model showing solar path analysis, used to simulate a building’s performance as part of the SBEM assessment process

A Design Stage assessment is entirely desk-based, run from drawings and specifications before construction starts. An As-Built assessment usually isn’t: it needs evidence that the completed building matches what was designed, which typically means an on-site audit alongside supporting certificates – air permeability test results and commissioning certificates among them. Some projects combine the two: for St Werburghs City Farm, we paired on-site diagnostic testing with SBEM modelling under the PAS 2038 methodology, giving the assessment a full picture of the buildings’ actual performance rather than relying on drawings alone.

To avoid delays once an assessment starts, have the following ready:

For As-Built assessments, add site access and any test certificates already in hand, such as air permeability results.

Turnaround depends on the building’s complexity and how complete the information provided is, but we work to a standard two-week turnaround, with most reports and certificates delivered inside that window.

What’s Next?

Whether you’re gathering information for a first submission or trying to understand why an As-Built assessment is taking longer than expected, knowing what the process actually involves makes it easier to keep a build programme on track.

We carry out SBEM assessments at both Design Stage and As-Built for new-build, extension, change-of-use and shell-and-core-to-fit-out projects across the South West and nationwide.