Wales is introducing its own 2026 Approved Documents L and F on 4 March 2027, 20 days before England’s Future Homes Standard takes effect. The two regimes look similar on the surface, because both expect heat pumps, rooftop solar and tighter ventilation standards. However, they are separate rulebooks with separate dates, targets and notional specifications, so a house type that passes in England is not guaranteed to pass in Wales. This guide is for housebuilders, developers, architects and technical teams building in Wales, or on both sides of the border. It covers what changes, how Wales differs from England, and what to do before the transitional window closes.
In this blog you’ll learn:
- The confirmed dates for Welsh Part L and F, including how plot-by-plot transitional protection works
- What the new notional dwelling, Energy Use Intensity target and solar PV requirement ask for
- How the Welsh rules differ from England’s Future Homes Standard
- What the Part F ventilation and commissioning changes mean on site
- Where Part O overheating fits, including the changes confirmed for existing homes in November 2026
- Practical steps to take before 4 March 2027
Confirmed Dates for Welsh Part L and F
Wales doesn’t use the “Future Homes Standard” name. Instead, the Welsh Government is introducing 2026 versions of Approved Document L and Approved Document F through the Building etc. (Amendment) (Wales) Regulations 2026.
The Timeline
- 6 March 2026 – The Welsh Government issued Circular WGC 003/2026, confirming the new energy efficiency regulations
- 7 April 2026 – Circular WGC 006/2026 announced the publication of Approved Document L (Volumes 1 and 2) and Approved Document F (Volume 1)
- 4 March 2027 – The Part L changes and the new Approved Documents take effect for building work in Wales
- 3 March 2028 – The last day for work on each protected building to be regarded as commenced
Transitional protection works building by building, not site by site. A building notice, initial notice or full plans application must be in before 4 March 2027, and work on that building must be regarded as commenced by 3 March 2028. On a site with several houses, only the buildings where work has commenced keep the old rules, according to the circular. As a result, registering a whole site does not protect plots that haven’t started.
“Commenced” has a specific meaning in Wales. For a new house, it means the sub-surface structure is complete: all foundations, any basement and the structure of the ground floor. Starting to dig does not count. The Welsh Government also intends to close the older 2010 and 2014 transitional routes, after 91% of consultation respondents supported the proposal.
What the Welsh Part L 2026 Standard Requires for New Homes
New homes are tested against a notional dwelling – a theoretical home of the same size and shape with a standard specification. The Welsh version is built around electric heating and rooftop solar.
A Heat Pump, dMEV and Solar Benchmark
The notional dwelling in Appendix E of Approved Document L, Volume 1 includes:
- An air source heat pump with low temperature radiators designed for a 45°C flow temperature
- Decentralised mechanical extract ventilation (dMEV) with a specific fan power of 0.15 W/(l/s)
- Air permeability of 4.0 m³/(h·m²) at 50 Pa
- External walls at 0.13 W/m²K, roof at 0.11 W/m²K and floor at 0.11 W/m²K
- Windows and glazed doors at 1.2 W/m²K
- Lighting at 105 lm/W
The Welsh Government chose this option after consultation. Its consultation modelling put the carbon reduction at 93% against Part L 2022, for a 3.3% increase in capital cost, averaged across a typical mix of house types. That figure was for the consultation draft. The final specification is slightly tighter, because external walls moved from 0.15 to 0.13 W/m²K after respondents objected to the relaxation.
This specification is a benchmark, not a design instruction. You can use a different mix of measures, provided the dwelling still meets the targets. The Approved Document also includes an alternative MVHR specification, with 1.5 m³/(h·m²) air permeability and 0.18 W/m²K walls, for teams with MVHR experience. The government kept MVHR out of the default because it would effectively make MVHR the only way to comply.
In addition, minimum fabric standards remain as a legal backstop. For new houses, Table 3.1 sets maximum U-values of 0.18 W/m²K for walls, 0.13 for roofs and 1.4 for windows, with an air permeability limit of 8.0 m³/(h·m²) at 50 Pa. These backstops stop a design from trading away fabric performance for extra solar PV.
Energy Use Intensity Replaces the Old Efficiency Rating
A new home must now pass four tests: the target primary energy rate, the target emission rate, the target fabric performance values and a target Energy Use Intensity (EUI). EUI is measured in kWh/m²/year and replaces the Dwelling Energy Efficiency Rate, which set a minimum energy efficiency rating of band B (81) for new homes.
EUI covers all energy use in the home, regulated and unregulated, so appliances count. Solar electricity used in the home also counts towards it. However, electricity exported to the grid does not. Wales also keeps its fabric performance values under regulation 26B, rather than adopting England’s fabric energy efficiency target.
Mandatory Rooftop Solar: Requirement L2A
Part L now includes a new requirement, L2A, to install a renewable electricity system on-site when a dwelling is erected. For a house, the reasonable output is an annual yield at least equal to a reference array with these characteristics:
- 0.22 kWp per m² of panels, over an area equal to 40% of the ground floor area
- Orientated south-east to south-west
- A 45 degree pitch
- No overshading
Buildings containing flats have equivalent building-level and dwelling-level options. Where a roof can’t reach the reference output, the guidance asks designers to maximise the reasonably practicable area, using the layouts in Appendix B, and to give building control the evidence. In exceptional cases, where the roof can’t support an annual output of 720 kWh, the guidance treats the requirement as not achievable. Off-site generation, such as a microgrid, can also count if equivalent output is directly available and prioritised for residents.
One detail matters for design: the solar in the notional dwelling matches what you install, up to the minimum. As a result, only panels beyond the reference array improve your result against the targets.
Heating, Terraces and Other Changes
- Heating fuels. Heating and hot water in new dwellings must use fuels with a CO₂ factor of 0.086 kgCO₂/kWh or less and a primary energy factor of 1.969 kWhPE/kWh or less, or a district heat network. In practice, this points to heat pumps, as the notional dwelling assumes.
- Flow temperature. All parts of a new wet heating system should be sized to run at a maximum flow temperature of 45°C.
- Terraces. Averaging targets across dwellings is only available within a building containing flats. Separate buildings on one site, and rows of terraced houses, must each be assessed individually.
- Chimneys. The guidance says not to provide a chimney or flue where no appliance is installed.
- Home Energy Guide. New homes need both a paper and a digital copy.
Compliance is demonstrated using SAP 10.3 for now. The Approved Document already references the Home Energy Model (HEM) for later, but HEM isn’t yet approved for Welsh Part L. Our SAP calculations team can run the Welsh targets in the interim, and our Home Energy Model guide explains what HEM changes.
Part F: Ventilation and Commissioning
Airtightness and ventilation are linked, so the Part L changes feed straight into Part F.
- Mechanical ventilation becomes the likely route. A dwelling with a design air permeability below 5 m³/(h·m²) at 50 Pa, or an as-built result below 3, counts as “highly airtight”. The natural ventilation guidance in Approved Document F only covers less airtight dwellings. At the notional 4.0, that points towards continuous mechanical ventilation, either extract-only or MVHR.
- Commissioning needs a competent person. Mechanical ventilation must be commissioned, and building control must receive a commissioning notice. In new dwellings, airflow rates must be measured and the results notified. The person commissioning should belong to an organisation that independently verifies competence, such as a competent person scheme.
- Powered flow hoods replace vane anemometers for continuous fans. Airflow from continuous extract and supply fans should be measured with a powered flow hood. A vane anemometer is only an alternative for intermittent extract fans. The device must be accurate to ±5% and calibrated with its hood within the last 12 months at a UKAS-accredited centre.
- dMEV ducting is limited. Rigid ducting should be used, with runs kept to 2.0 m where practical. Longer runs need design calculations for building control.
Every new dwelling also still needs an air pressure test, following CIBSE TM23. Both air tightness testing and ventilation testing therefore stay on the critical path for Welsh handovers.
Wales vs England: What’s Different
Both countries are tightening Part L and F in March 2027, but the detail differs in ways that affect compliance.
- Name and date. Wales brings in Part L 2026 on 4 March 2027. England brings in the Future Homes Standard on 24 March 2027 (24 September 2027 for higher-risk building work).
- Transitional rules. Both protect plots individually. In Wales, the notice must be in before 4 March 2027 and work must be regarded as commenced by 3 March 2028. England follows the same pattern, with dates about three weeks later and the same commencement threshold.
- Performance targets. Wales tests primary energy, emissions, fabric performance values and EUI. England’s third target is fabric energy efficiency.
- Flow temperature. Newly installed wet heating systems are sized for a maximum of 45°C in Wales and 55°C in England.
- Solar PV. The reference array is the same in both (0.22 kWp/m² over 40% of the ground floor area, south-east to south-west, 45 degrees, 720 kWh exceptional threshold). The requirement is labelled L2A in Wales and L3 in England.
- Compliance tool. Both start with SAP 10.3. England expects HEM in the second half of 2027. Wales has no date yet, because the Welsh Government plans to produce its HEM tool after England’s implementation.
So, if you build on both sides of the border, model each house type against both regimes.
What About Part O Overheating?
The Welsh Government’s Part O changes target existing homes, not new builds. Part O still shapes new-build design, though. The notional dwelling in Part L copies your actual g-value, so the energy model won’t flag glazing choices that drive overheating. Part O compliance has to catch that separately.
We already carry out Part O overheating calculations plot by plot in Wales, including for Redrow, and our guide to TM59:2026 explains the updated methodology.
Redrow Homes, Churchlands: Delivering Part O Compliance Across Mixed Apartments and Houses
View Case StudyIn November 2026, the Welsh Government confirmed it intends to go ahead with these changes for existing dwellings:
- Solar control measures when replacing windows and doors in highly glazed flats, where glazed area exceeds 15% of the flat’s total floor area, with a maximum g-value of 0.40
- New guidance for loft conversions to habitable rooms where glazing exceeds 15% of the conversion’s floor area, applying only to the new room or rooms
- Extra commentary in Approved Document O on highly glazed extensions
The final Approved Document O and amending regulations are expected in 2027, taking effect six months after publication.
Our Expert Insights: Preparing Plots for March 2027
Our technical team recommends six checks for any Welsh plots that will fall under the new rules.
- Map plot status first. List which buildings have a notice or plans in before 4 March 2027, and which can reach commencement (foundations and ground floor structure complete) by 3 March 2028. Everything else falls under Part L 2026.
- Model every house type against the Welsh targets. Run each type through SAP 10.3 against the Welsh notional specification, including the EUI target. Don’t reuse English results, because the targets and heating assumptions differ.
- Check each roof for L2A early. Work out the 40% ground floor area reference array, then test whether the roof can reach it. If not, document the maximised layout before the design is fixed.
- Assess each terraced plot individually. Averaging isn’t available for rows of terraced houses.
- Plan ventilation and testing together. At the notional 4.0 airtightness, expect continuous mechanical ventilation. Book commissioning by a competent person with a powered flow hood, alongside the air pressure test.
- Size heating for 45°C. Check emitters and pipework early, because a lower flow temperature affects radiator sizes.
What’s Next?
The Welsh standard is confirmed, and the dates are fixed. The practical work now is to sort plots by transitional status, then model the remaining house types against the Welsh targets while there is still time to change specifications. Because Wales and England differ on dates, metrics and heating assumptions, treat them as two separate compliance exercises. Our building compliance team supports housebuilders through both.
We model standard house types against the Welsh Part L 2026 targets using SAP 10.3, so you can see where a specification fails before it reaches site. If you’d like your Welsh plots checked, our team can talk you through what that looks like for your portfolio.